Flood Mitigation

Stonbury was contracted by the Environment Agency to complete an initial vegetation cut, followed by other flood mitigation measures on an 800-metre stretch alongside the River Isbourne.

The area has experienced significant flooding issues in the past, most notably in 2008. The high banks had been allowed mature with little maintenance, and this had reduced the attenuation and conveyance of flood water. The flood scheme was designed to strategically slow water above the village and move it downstream swiftly.

The initial vegetation cut was made from the shallow water course so working within the channel could be avoided once the salmonid spawning season began. Vegetation was removed from the channel bed up to the top of the banks and from around in-channel structures such as outfall headwalls, bridges, and flood walls. Trees under 200mm in diameter were also removed.

Due to the sensitive nature of the works, Stonbury engaged an Ecological Clerk of the Works (ECoW). When they first arrived on site, they provided a toolbox talk covering all areas of work. Once the initial cut was complete, several other flood mitigation activities were undertaken

Bat Survey

The stand of seven to eight trees had low value for roosting bats but as a precautionary measure they were gently soft felled using tree shears that allowed further safe inspection once on the ground by the ECoW who were licensed to carry out the work. Any large trees over 200mm and at the top of the bank were left standing.

Hedge Machine Cutting

The further clearance of shrubbery and trees on the top of the bank was overseen by the ECoW and particular attention was paid to the hedge where there may have been dormice.

Fence Line Recommission

The cattle drinking areas were heavily poached, which increases turbidity in the stream and is damaging to potential salmonid spawning gravels, therefore these areas were fenced and a solar powered solution will be installed to provide pumped water from the river to satisfy the riparian landowners’ farming requirements. The protected areas were planted with approximately five thousand hedge whips of a variety of native species, in biodegradable guards. These measures enable the project to achieve biodiversity net gain.

Silt Berm Removal

The silt bank below the road bridge causes a significant blockage and reduces stream capacity. After investigating removal options including air lift and suction, the team decided to mobilise a small machine to dig out approximately two hundred cubic meters of silt, which is placed on the opposite bank and allowed to vegetate.

The Environment Agency provided excellent feedback on the teams engagement with the local community and environmental mitigation measures.

Download a PDF of this project