Service reservoirs play a key if sometimes unsung role, in the supply of clean water within the UK.
The refurbishment of one such service reservoir dating back over a century has given it an additional 30-year lease of life at a fraction of the cost of building a new one. Undertaking this project did not come without its technical challenges.
In common with a large number of service reservoirs, Malpas Service Reservoir, owned and operated by United Utilities, dates back many years. The 20.5ML balancing reservoir was built in 1913 close to the village which gave it its name and lies close to the southern border of Cheshire, a few miles from the border with Wales.
Then, as now, it formed an important ‘staging post’ for water flowing from Lake Vyrnwy in North Wales into the North West. Lake Vyrnwy was constructed in the 1880s with a capacity of 59.7GL, originally to supply water to Liverpool via a 68-mile aqueduct constructed by Liverpool Corporation. Other pipelines were subsequently added, and the water from Lake Vyrnwy now forms part of a network of sources supplying a much wider area.
Today, the Malpas Reservoir helps service a population across a wide area of Cheshire. And while originally it was built as an open tank for clean water storage, after regulations changed, the circular tank was enclosed with a steel-clad roof.
Having served its purpose well for over a hundred years, time has now taken its toll on Malpas. Recent investigations discovered water ingress to the tank and the existing brickwork walls were found to be in a poor state. Stonbury, specialist contractors to the water industry, were commissioned to undertake a comprehensive internal refurbishment together with some external repairs.
The roof vents to the service reservoir were found to be allowing in rainwater, and so works to the roof were to be carried out internally and externally. This required erecting scaffolding and an extensive area of safety netting. External access to the roof also posed safety risks as the roof had a low load bearing capacity.
In addition, the contract came with a tight deadline of just 12 weeks because of the need to get the reservoir back into use to meet the higher customer demand of water in late spring. A very high quality surface internal finish was required, to ensure that the reservoir will provide the maximum service length after completion.
Stonbury assigned a team of 15 full time personnel to the project, including specialist contractors for the steel fabrication and construction of new stainless steel stairs within the reservoir. Work commenced in November 2016 and was completed in early April 2017.
The project commenced with overbanding to the floor joints, applying the longer lengths first while keeping the joints clean ready for the welding. Ultimately, some 3804 metres of overbanding were required to cover the 3849m2 of flooring creating a spider web effect in the circular-shaped reservoir.
Priority was given to completing the joints near the flume first, so it could be fixed back into position. At the same time, another team commenced grit blasting the walls to prepare them for resurfacing, as well as cleaning the other surfaces; including the steelwork within the reservoir. Work started first on the walls at the lower section, allowing regular checks on the profile to ascertain if the amount being removed was adequate and even.
Specialist engineers then undertook a detailed survey of the roof vents (which had been allowing in rain water) and the grating to the floor channel to determine the scope of work required, while the blasting grit was removed from the reservoir floor by another team.
By week 6 of the project, the overbanding to the floor of the reservoir had been successfully completed, and the internal surface of the reservoir walls, comprising Staffordshire blue engineering bricks, had been sufficiently prepared for mesh to be fixed to the walls across 24 bays and a total area of 1200m2. Fixing the mesh, which ultimately took a total of 15 days, created a suitable surface for the concrete spray to be applied. In total, 55,000 litres of concrete spray were applied to the perimeter walls. Timber screed rails were then fixed into place and spraying of the reservoir walls began in week 5, once the mesh had been applied in the first few bays.
To stay in line with the contract schedule, a target of completing the spraying of one bay a day was set, while mesh fixing continued on the remaining bays. Progress was slowed somewhat with numerous spray pump breakdowns, putting the concrete spraying two days behind schedule at one point, requiring weekend working to regain time. Work on the grating was completed in week 7 to cover the outlet channel.
During week 9 of the contract, a separate team erected scaffolding and fixed safety netting to the internal roof, providing safe internal access to the vents. During this week, steel fabrication contractors also came on site to install a series of channel covers inside the reservoir. Because the metal roof would not safely withstand the weight of people working on it, scaffolding was erected in several places over the top, together with a series of safety lines to provide safe external access to the vents. With the roof vents fixed in place, a Davit Arm and an SS ladder were introduced; and these, together with the scaffolding, provided safe access for the internal steel surfaces in the roof to be coated.
With the concrete spraying nearing completion, work then commenced on the perimeter walls overbanding, applying some 120m of overbanding to seal the joints between the 24 bays.
In the final week, all plant and equipment were removed, final tests conducted to ensure the water tightness of the overbanding and the site cleared and cleaned ready for inspection. A new handrail was installed on the top landing area and bracing applied to the newly installed access ladder. The final inspection was conducted by the client and the project was deemed completed and handed over.
Stonbury, one of the largest contractors in this sector of the water industry, typically undertakes around 450 refurbishment projects of this nature every year, making the process fairly standard for Stonbury and their supply partners. The ageing nature of our water supply infrastructure, and the cost of replacing it, means that retaining the structures that can be refurbished should represent a very worthwhile investment where it is technically feasible and financially viable. Moreover, there is a wealth of knowledge within the sector on the best techniques and materials to use, and considerable experience gained over the years on tackling projects of this nature to anticipate likely problems after work commences and factor these into contract tenders.