We completed a major refurbishment project at a strategically important water treatment works, extending the lifespan – by over 10 years – of a critical asset whilst mitigating the need for a costly and carbon intensive new build alternative.
Storm tank installation
A 55 cubic metre sectional-steel storm tank with sustainable features was installed at a wastewater treatment site to comply with regulations to cut sewage overflows. The works significantly reduced running costs for our client and allowed them to meet specified carbon reduction targets while increasing stormwater capacity to help protect local waterways for decades to come.
Large-scale weir removal
On behalf of the EA we successfully opened 340 miles of catchment in the largest project of its kind – in the country – by removing a 70 meter wide, 900 year old medieval weir. Removing the weir significantly improved fish migration, spawning grounds and habitat. Fallen water levels have also allowed natural ecological processes to recommence.
Steel sludge holding tanks refurbishment
Stonbury, specialist contractors to the Water Industry, have recently completed the internal refurbishment of 2 steel sludge holding tanks.
Filter tank refurbishment
As part of a wastewater framework, Stonbury was enlisted to complete refurbishment works to a filter tank in the north of England.
Steel tank refurbishment
Stonbury refurbished a steel potable water tank to prolong its length of service by two decades.
Steel water tower demolition
Stonbury were contracted to optioneer and price for the demolition of an abandoned water tower in the north of England.
Start up to waste bag replacement
Stonbury attended an emergency response to replace a Start Up To Waste (SUTW) bag on a wastewater treatment site in the Northwest after the existing bag had failed.
Storm lake refurbishment
Stonbury was enlisted to undertake various works to refurbish a storm lake, including flood alleviation, access improvements and and concrete repairs to the inside of the lake wall.
Storm tank repairs
Stonbury was enlisted to complete emergency repairs to a storm tank floor after leakage was discovered through several areas in the floor.
Surge vessel access & lining refurbishment
As part of an ongoing inspection and maintenance programme, Stonbury was contracted to carry out refurbishment works to one of the client’s surge vessels.
Surge vessel refurbishment
Stonbury was contracted for the refurbishment of 3 No surge vessels after an inspection highlighted the manways did not conform to the current confined space specification.
Embankment and flood wall repairs
Stonbury were recently contracted to repair damage caused by badgers under-mining the tidal embankment and flood wall at a popular holiday resort on the coast.
Water liner installation
Stonbury were recently asked to inspect a reservoir that required some minor remedial works, including repairs to the exposed roof joint, however substantial ingress through the floor slabs and the adjacent redundant tank was quickly identified.
Water tower roof refurbishment
Stonbury was contracted to extend the life of a water tower in the South of England. This included the removal and replacement of the entire roof slab.
Water treatment works contact tanks refurbishment
Stonbury were recently awarded the contract for the repair and refurbishment of internal contact tanks within a Water Treatment Works facility.
Critical asset repairs
Earlier in the year, we began carrying out repairs to a failing reservoir which showed signs of severe water ingress. The original scope included 180 linear meters of crack repairs. However, following an inspection, this increased to more than 300.
Dam and watercourse refurbishment
A county council contracted Stonbury to carry out a package of repair works to dams and watercourse at various locations.
Weir & dam refurbishment
We were contracted after lengthy client/designer/contractor investigation works to complete the full refurbishment of 10 No. weir and dam structures near Burton upon Trent.